UNIVERSITY OF TECHNOLOGY SYDNEY (TECH LAB)

Ripa Concrete Cutting was called in by Shape Australia Pty Ltd when a reaction wall inside a testing facility within UTS failed under pour causing the finish to be unviable.  A methodology was put in place for the corrections with entailed Ripa Concrete Cutting using their Track Mounted Wall Saw to saw cut every 10mm at a tolerance of 1mm. In order for this to be done, Ripa Concrete Cutting had to make custom structural steel jigs on a roller system to mount the Wall Saw too in order to achieve the desired tolerance. This equated to over 2.4km of saw cutting. We also designed and installed a plastic bubble prior to commencement of works which assisted with slurry and dust control. The works took 2 weeks to complete and is now able to be used as intended.

PROJECT HIGHLIGHTS

Cut more than 2400m of saw cutting using the Hilti Track Mounted Wall Saw every 10mm at a tolerance of 1mm

Designed and engineered custom structural jigs on a roller system for the Wall Saw to mount

Related Services

bottom of page